Simon Contractors Gets $2.74 M Scottsbluff Road Project

Simon Contractors Gets $2.74 M Scottsbluff Road Project
Curb work related to the 20th Street mill and overlay was completed earlier in the year, paving the way for the rest of the project (KNEB/RRN file photo)
March 4th, 2024 | Ryan Murphy

A Cheyenne based firm with a Scottsbluff office is the recipient of a multi-million dollar road project.

Simon Contractors was the only bidder for a mill and overlay on Scottsbluff’s 20th Street from Cleveland Field to 17th Avenue.

Their $2.74 million bid was approximately 12% higher than the engineer’s estimate, but also had increased material costs and higher than anticipated traffic control costs.

The council gave unanimous approval to award the contract to Simon, and the project has an October 1st anticipated completion date.